Critical Path
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Ronal and Dieter,
I got it . That is great .
Thank you very much .
Reagrds
Jia yin
Longest Path is a process, similar to but different from CPM and total float. Longest path is a better measurement of the critical path than using total float, as tracking total float ‘fails’ in instances where multiple activity calendars, LOE, interruptible activities, resource leveling, constraints, and out-of-sequence activities are used. I have an article published on the web about this and enhancements to longest path at http://ronwinterconsulting.com/published.htm. Good luck!
Hi Jiayin
The reason is a very simple one:
Primavera does calculate with decimals. If youll change your preferences that decimals will be displayed, youll realize that those activities you are missing have a float of 0. which is greater than zero.
Edit --> User Preferences --> Time units --> Show decimals
Regards
Dieter