Incorrect Durations Showing

M
Matthew Lovkis 👤 Member for 19 years 6 months

Thanks a lot folks.



It was that simple. The default calendar was incorrect for the schedule.



Cheers,



Matt

T
Taher Abdel-Aziz 👤 Member for 22 years 1 month

Hi Matt,

Be sure that the default calender is the same project calender. Primavera use the default calender in rolling up the duration information regard less the project calender.

Hope this help,

Taher

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Matt,



Check your Hours per Time Period setting. Make sure it match to your calendar settings. Durations are calculated from the Hours per Time Period which can be set on Admin preference or User preference under Time Units Tab if “Allow users to specify the number of hours for each time period” is tick.



Hope this help,

Rodel


Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts