Incorrect Durations Showing
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks a lot folks.
It was that simple. The default calendar was incorrect for the schedule.
Cheers,
Matt
Hello,
I agree with Taher.
We already spoke earlier about this topic. Please refer to http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=8&Top=33537
Kindest regards.
Patricia
Hi Matt,
Be sure that the default calender is the same project calender. Primavera use the default calender in rolling up the duration information regard less the project calender.
Hope this help,
Taher
Hi Matt,
Check your Hours per Time Period setting. Make sure it match to your calendar settings. Durations are calculated from the Hours per Time Period which can be set on Admin preference or User preference under Time Units Tab if “Allow users to specify the number of hours for each time period” is tick.
Hope this help,
Rodel