Negative Float & Constraints - Primavera P5

F
France Tintinger 👤 Member for 19 years 4 months

Hi Mike

Spot On!!

You are a genius. I found the culprits in the "External Late Finish" column. I deleted these and ran the schedule. All the negative floats are gone.

Thanks a lot for your help.



regards



France

V
VENKAT RAMANA 👤 Member for 19 years 4 months

In a possible way for your solution..try the following which can help you to an extent..



Choose Project, Activities, then select the activity whose constraint you want to define.Display Activity Details, then click the Status tab.In the Primary field, select a constraint type.Click in the Date field, then select the date to which the constraint applies.In the Secondary field, select a constraint type (if necessary).Click in the Date field, then select the date to which the constraint applies.



The Secondary constraint list is filtered based on the value you select in the Primary constraint field.You cannot apply constraints to Level of Effort or WBS Summary activity types.



Regards,



VENKAT


M
Michael Hunter 👤 Member for 19 years 4 months

Donovan / France



Another possibility:

If you had relationships to activities in another schedule then the constraints may arise from dates held in the "External Dates" field which are not necessarily displaid in the Activities Details Tab.



Mike

F
France Tintinger 👤 Member for 19 years 4 months

Thanks for your suggestions Donovan.

I have checked all the things you have mentioned except for the baseline suggestion. I will try it and let you know.

D
Donovan Govender 👤 Member for 20 years 6 months

did remove your actuals in labour units,and durations, and maybe its in your baseline







regards

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts