In a possible way for your solution..try the following which can help you to an extent..
Choose Project, Activities, then select the activity whose constraint you want to define.Display Activity Details, then click the Status tab.In the Primary field, select a constraint type.Click in the Date field, then select the date to which the constraint applies.In the Secondary field, select a constraint type (if necessary).Click in the Date field, then select the date to which the constraint applies.
The Secondary constraint list is filtered based on the value you select in the Primary constraint field.You cannot apply constraints to Level of Effort or WBS Summary activity types.
Regards,
VENKAT
Member for
18 years 9 months
Member for18 years9 months
Submitted by Michael Hunter on Tue, 2007-02-13 03:21
If you had relationships to activities in another schedule then the constraints may arise from dates held in the "External Dates" field which are not necessarily displaid in the Activities Details Tab.
Mike
Member for
18 years 9 months
Member for18 years9 months
Submitted by France Tintinger on Tue, 2007-02-13 02:01
Member for
18 years 9 monthsRE: Negative Float & Constraints - Primavera P5
Hi Mike
Spot On!!
You are a genius. I found the culprits in the "External Late Finish" column. I deleted these and ran the schedule. All the negative floats are gone.
Thanks a lot for your help.
regards
France
Member for
18 years 8 monthsRE: Negative Float & Constraints - Primavera P5
In a possible way for your solution..try the following which can help you to an extent..
Choose Project, Activities, then select the activity whose constraint you want to define.Display Activity Details, then click the Status tab.In the Primary field, select a constraint type.Click in the Date field, then select the date to which the constraint applies.In the Secondary field, select a constraint type (if necessary).Click in the Date field, then select the date to which the constraint applies.
The Secondary constraint list is filtered based on the value you select in the Primary constraint field.You cannot apply constraints to Level of Effort or WBS Summary activity types.
Regards,
VENKAT
Member for
18 years 9 monthsRE: Negative Float & Constraints - Primavera P5
Donovan / France
Another possibility:
If you had relationships to activities in another schedule then the constraints may arise from dates held in the "External Dates" field which are not necessarily displaid in the Activities Details Tab.
Mike
Member for
18 years 9 monthsRE: Negative Float & Constraints - Primavera P5
Thanks for your suggestions Donovan.
I have checked all the things you have mentioned except for the baseline suggestion. I will try it and let you know.
Member for
19 years 11 monthsRE: Negative Float & Constraints - Primavera P5
also check wether predeccessors or succesors are linked to fixed dates
Member for
19 years 11 monthsRE: Negative Float & Constraints - Primavera P5
did remove your actuals in labour units,and durations, and maybe its in your baseline
regards