Abhijeet,



I found out that if the activity doesn’t have a resource assigned to it, the expense assigned to that activity wouldn’t export to P3; so what I did is basicaly:



1) assigned a dummy "redundant" resource to those activties with no resource but have expense! in P3e.



2) exported the project to P3.



3) Removed the Dummy Resource in P3; ofcourse the expense was exported this time and problem solved :)

A
Abhijeet Ranadhir 👤 Member for 19 years 11 months

I exported my schedule from P 5.0 to P3 and all the expenses did transfer. I think there is a cost account available in p3 to assign expenses. Do you know anything about it?