I found out that if the activity doesnt have a resource assigned to it, the expense assigned to that activity wouldnt export to P3; so what I did is basicaly:
1) assigned a dummy "redundant" resource to those activties with no resource but have expense! in P3e.
2) exported the project to P3.
3) Removed the Dummy Resource in P3; ofcourse the expense was exported this time and problem solved :)
I exported my schedule from P 5.0 to P3 and all the expenses did transfer. I think there is a cost account available in p3 to assign expenses. Do you know anything about it?