"SS+Lag" or "FF"
Forum Sponsor
Top Posters
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
It should start on day 9 (i.e a 2 day task will occupy days 9&10 to finish coincident with a 10 day activity.
What makes you think that this would be unfavourable ?
Hey Steven,
Thanks for your response.
In FF case, the successor task will be planned to start latest possible. Task A= 10 days, Task B=2 days. Defining B as successor to A with FF relationship, will plan B to start on day 8, which is not very favorable.
Am I right?
Nozar
My preference would be FF, as the start of the successor is then dicated by the progress of the predecessor.