"SS+Lag" or "FF"

S
Steven Oliver 👤 Member for 23 years 7 months

It should start on day 9 (i.e a 2 day task will occupy days 9&10 to finish coincident with a 10 day activity.



What makes you think that this would be unfavourable ?


N
Nozar Naghani 👤 Member for 21 years 11 months

Hey Steven,

Thanks for your response.

In FF case, the successor task will be planned to start latest possible. Task A= 10 days, Task B=2 days. Defining B as successor to A with FF relationship, will plan B to start on day 8, which is not very favorable.

Am I right?



Nozar

S
Steven Oliver 👤 Member for 23 years 7 months

My preference would be FF, as the start of the successor is then dicated by the progress of the predecessor.