Drive Activity Dates by Default
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks Arnold!
Default Unit/Time under Resource was zero. I changed it to 1 and now it is ok.
Hi Kaide,
If I understood you correctly, go to project details --> calculations tab, try to play with "Reset Original Duration and Units to Remaining" or "Reset Remaining Duration and Units to Original". I am not sure, just try this.
Otherwise, try to check your Defaults Units/Time in Resources Window, it should not be blank or Zero. There should be a value (e.g. 8 or any value).
Regards,
Arnold