Drive Activity Dates by Default

K
Kaide Johar Manasi 👤 Member for 20 years 1 month

Thanks Arnold!

Default Unit/Time under Resource was zero. I changed it to 1 and now it is ok.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Kaide,



If I understood you correctly, go to project details --> calculations tab, try to play with "Reset Original Duration and Units to Remaining" or "Reset Remaining Duration and Units to Original". I am not sure, just try this.



Otherwise, try to check your Defaults Units/Time in Resources Window, it should not be blank or Zero. There should be a value (e.g. 8 or any value).



Regards,



Arnold