baseline vs as built

J
jack scott 👤 Member for 10 years 11 months

A while back, I was working on a claim.  Using P3, I superimposed the as built schedule onto the baseline schedule.  Unfortunately, I can't remember how I did it.  Any help?  Also, does Suretrak have this function?

Thanks!

Z
Zoltan Palffy 👤 Member for 16 years 10 months

how you do it in p3 is to

openthe project

go to tools

select project utilities

select targets this is where you would select the baseline 

then select forrnat bars 

select modify in the drop donw by where it says structure

for the start point select target 1 early or late start

for the end point select target 1 early or late finish 

upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jack

This is how I would do it.

Open the original programme.

Change the durations to the as built dates.

DO NOT SAVE IT.

Create an undelying baseline.

Close the file and DO NOT SAVE It.

Open the file and you have the as built underlying the as planned.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts