A while back, I was working on a claim. Using P3, I superimposed the as built schedule onto the baseline schedule. Unfortunately, I can't remember how I did it. Any help? Also, does Suretrak have this function?
Thanks!
A while back, I was working on a claim. Using P3, I superimposed the as built schedule onto the baseline schedule. Unfortunately, I can't remember how I did it. Any help? Also, does Suretrak have this function?
Thanks!
how you do it in p3 is to
openthe project
go to tools
select project utilities
select targets this is where you would select the baseline
then select forrnat bars
select modify in the drop donw by where it says structure
for the start point select target 1 early or late start
for the end point select target 1 early or late finish
upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar
Hi Jack
This is how I would do it.
Open the original programme.
Change the durations to the as built dates.
DO NOT SAVE IT.
Create an undelying baseline.
Close the file and DO NOT SAVE It.
Open the file and you have the as built underlying the as planned.
Best regards
Mike Testro