actual curve in p3 from tabular report

 

Dears,

I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it

 

Sorry for my bad language

 

Regards 

R
Rafael Davila 👤 Member for 22 years 3 months

Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical.

Plan = Remaining Work after DD

Photobucket

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts