How can change the date display type in P3.
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Robin,
In P3, Click Format>Dates and only appeared the date format for Arabic numerals(21-3-2010), but not had that I need type (21-mar-2010)on months.
In P3, Click Format>Dates and then Select the date format you want.
Hi Mike,
Sorry! I wrote the status is in primavera - P3.1 Verson. whether is same changing on the default system of windows XP? I already try so doing but not change together with system of windows XP.
Best regards
Mch714
Hi Mch
It is old software so the numeric system applies - you are lucky to get 2010 visible.
In Powerproject version 5 - some time ago - the date format was linked to the default windows set up but now you can set it to whatever configuration you want.
Best regards