hi
check this formula ,i thrust it would be useful to you
Driving Resource Duration = Quantity to complete / units per time period
1- You need to estimate the Qty. for each resource assigned to the activity
2-Find the average productivity for each
3- Specify the availability for each resource
4- Mark the driven resources
Then the biggest duration will be considered, which is already calculated as a result for the steps 1-4 above
could you explain me, the method please
Yes of course