P6 WBS is Hierarchy is mismatching in activity Window

R
Rajkumar S 👤 Member for 14 years 7 months

Hi, I required troubleshooting in my P6, The WBS Hierarchy sequence is not followed in my activity window in my P6. This started when I imported an external .exr file into my P6. My whole P6 has started to follow the WBS disturbance. The screenshots are enclosed. Anyone Welcome to provide a solution. Thank you

wbs_1.jpgwbs_2.jpg

D
david kelly 👤 Member for 10 years 3 months

You should always zero fill in P6.

For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1

Just overtyping the WBS code with the new zero filled values should sort it