Hi, I required troubleshooting in my P6, The WBS Hierarchy sequence is not followed in my activity window in my P6. This started when I imported an external .exr file into my P6. My whole P6 has started to follow the WBS disturbance. The screenshots are enclosed. Anyone Welcome to provide a solution. Thank you


You should always zero fill in P6.
For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1
Just overtyping the WBS code with the new zero filled values should sort it