primavera activity predecessor

J
John Bansag 👤 Member for 6 years 10 months

Sir/s:

 

I am new in Scheduling.

I started to learn Primavera but I stumble with the Primavera own sample scheduling the "City Center Office Building"

How could it be that thte predecessor of Activity EC1090 is also EC1090 (below window) predecessor.

 

Thank you for the answer.

 Image removed.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

good call Rodel

John in the predcessor window add a column for Project Id and that will tell you if it is linked to another project.

Also if it is linked there should be an astericks next to the start date for that activity

J
John Bansag 👤 Member for 6 years 10 months

I think you are right. you can find it actually in the sample database built-in in the primavera.

 

thank you

R
Rodel Marasigan 👤 Member for 19 years 8 months

The only reason that I can think off is you link an external activity (another project) with the same activity ID to your project.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

That is impossible an activity can not have itself as predcessor it wont let you 

also no window show below

look at it carefully maybe the zero is really an O in that ativity.

Forum Sponsor

Top Posters

Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts