Resources Assignment

U
Usman Yasin 👤 Member for 6 years 2 months

I am trying to assign resources to the activities but every time i do that, budgeted unit changes automatically. I checked my calendar, it is set on the exact requirement, but still the same issue.

Can anyone help?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that you duration type is fixed duration and units/time add a column and do the 1st one and then do a fill down

next go to Projectsand in the Default tab make sure that you duration type is fixed duration and units/time 