I am trying to assign resources to the activities but every time i do that, budgeted unit changes automatically. I checked my calendar, it is set on the exact requirement, but still the same issue.
Can anyone help?
I am trying to assign resources to the activities but every time i do that, budgeted unit changes automatically. I checked my calendar, it is set on the exact requirement, but still the same issue.
Can anyone help?
make sure that you duration type is fixed duration and units/time add a column and do the 1st one and then do a fill down
next go to Projectsand in the Default tab make sure that you duration type is fixed duration and units/time