Dear All,
I would like to develop a Schedule for Cable Fire Proofing incl. trays (Intumescent FireProofing cable coating)
Please let me know,
1. What kind of actvities involved in this particlualr work ?
2. What are the Constrains to be started this work ?
Please support me in this regards.....
glad I could help
Thank you dear
regards,
Thank you dear
regards,
1st you will need to survey the existing conditions to determine which cables that you want to fire proof
2nd you will have to prepare the immediate area around the cables that you want to fireproof doing things such as putting plastic on other items that you do not want to get the fire-proofing on.
3rd if possible install ventilation in the area where the fire-proofing is beiing performed
4th you will need to rope of the area where the fire-proofing is being sprayed on.
5th Spraying of the cables is next
6th you will have to clean up any remnants of the fire-proofing that did not adhear
7th remove the plastic that you previously installed
8th remove the ventilation that you previously installed
9th remove the barrier, rope or tape from the area that you previously quarended off
10th done