Weightages

R
Rahul MK 👤 Member for 13 years 4 months

While considering the project from Idea stage to Transfer of completed projects to operation, what should be the weightage for each stage i.e Idea, Study, Design, Implementation? Thanking you all in advance.

S
Suhaila Tsu 👤 Member for 15 years

Dear All

1. A schedule which is not correctly or completely loaded
cannot produce a complete plan%, right?

2. A schedule need to be cost loaded in order to get the schedule % complete at the WBS level and at the total roll-up.

J
Joseph Mbogo 👤 Member for 7 years 11 months

Build a matrix driven by Cost, Duration, Resources (Manpower) requirements.

The Weightage then will be clear where you have more and less. 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

whats your measuring stick ?

The Idea takes time

a Study Takes time

the Design takes time 

the Implementation takes time 

what do all of these have in common ? TIME

how is time measured ?

Usually in manhours 

So figured out the manhours for each of these stages and you have your weights 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts