While considering the project from Idea stage to Transfer of completed projects to operation, what should be the weightage for each stage i.e Idea, Study, Design, Implementation? Thanking you all in advance.
Weightages
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Zoltan, thank you for your affirmation.
Suhaila that is correct
Dear All
1. A schedule which is not correctly or completely loaded
cannot produce a complete plan%, right?
2. A schedule need to be cost loaded in order to get the schedule % complete at the WBS level and at the total roll-up.
Build a matrix driven by Cost, Duration, Resources (Manpower) requirements.
The Weightage then will be clear where you have more and less.
whats your measuring stick ?
The Idea takes time
a Study Takes time
the Design takes time
the Implementation takes time
what do all of these have in common ? TIME
how is time measured ?
Usually in manhours
So figured out the manhours for each of these stages and you have your weights