Good morningPlease am having issues when reporting, when ever i have to update the percentage work progress in it changes the finished date assigned to it by reducing the actual date and if i try to bring it back to the actual date that is assigned to it, it will reduce the percentage to zero percent. what is cause am confused in P6 Thanks
Problem on Updating
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
to update an activity 1st click the started box
2nd put in the actual date that it started
3rd put in the remaining duration
When in Activity View, select the Activity Details at the bottom of the screen, in the General Tab, check that the % Complete Type is set to Physical not Duration.
You may need to check for all activities - you can do this by adding the % Complete Type column to the activity view, changing one, select the ones you wish to change and then right-click and select "Fill Down"