Problem on Updating

Good morningPlease am having issues when reporting, when ever i have to update the percentage work progress in it changes the finished date assigned to it by reducing the actual date and if i try to bring it back to the actual date that is assigned to it, it will reduce the percentage to zero percent. what is cause am confused in P6  Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

to update an activity 1st click the started box 

2nd put in the actual date that it started

3rd put in the remaining duration

S
Santosh Bhat 👤 Member for 21 years 1 month

When in Activity View, select the Activity Details at the bottom of the screen, in the General Tab, check that the % Complete Type is set to Physical not Duration.

You may need to check for all activities - you can do this by adding the % Complete Type  column to the activity view, changing one, select the ones you wish to change and then right-click and select "Fill Down"

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts