XER file at completion units is changed.

Dear Friends

whenver i importing XER file at completion units is changed.

we are using server based software. means we are updating the programme multiple users.

and we are using unit percentage complete.

so please help...

Z
Zoltan Palffy 👤 Member for 16 years 10 months

what is your Resource assigment setting in the Projects directory ?

add actual to remaining or subtract actual from at completion ?

also do you have Recalculate Actual Units and costs when duration % changes ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts