Dear Friends
whenver i importing XER file at completion units is changed.
we are using server based software. means we are updating the programme multiple users.
and we are using unit percentage complete.
so please help...
Dear Friends
whenver i importing XER file at completion units is changed.
we are using server based software. means we are updating the programme multiple users.
and we are using unit percentage complete.
so please help...
what is your Resource assigment setting in the Projects directory ?
add actual to remaining or subtract actual from at completion ?
also do you have Recalculate Actual Units and costs when duration % changes ?