shchedule % complete problem in p^

hi , I have a question

when I use Update Progress ,, and my new data date is : 5 jun 2016 ,,,

but when I press Apply,,, 

in Schedule% Complete coloumn shows 100% for an activity which its finish date is 30 Oct 2016 .

i checked it,,seems everything is ok ,,i dont know where did I enter wrong ?

thank you so much.

Mina

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts