hi , I have a question
when I use Update Progress ,, and my new data date is : 5 jun 2016 ,,,
but when I press Apply,,,
in Schedule% Complete coloumn shows 100% for an activity which its finish date is 30 Oct 2016 .
i checked it,,seems everything is ok ,,i dont know where did I enter wrong ?
thank you so much.
Mina
My plan is in Primavera P6