Unit mhrs

Dear ALL,

For the contruction planning what will be the right method on the manpower histogram.

Do i need to basing the unit man hour from the contract B.O.Q or from the manpower estimation on each activity.

Any advise please...

Regard's

Ron

Z
Zoltan Palffy 👤 Member for 16 years 10 months

If you have the manpower estimate for each activity then you have the total is the Budgeted Quantity 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts