Dear ALL,
For the contruction planning what will be the right method on the manpower histogram.
Do i need to basing the unit man hour from the contract B.O.Q or from the manpower estimation on each activity.
Any advise please...
Regard's
Ron
Dear ALL,
For the contruction planning what will be the right method on the manpower histogram.
Do i need to basing the unit man hour from the contract B.O.Q or from the manpower estimation on each activity.
Any advise please...
Regard's
Ron
If you have the manpower estimate for each activity then you have the total is the Budgeted Quantity