Primavera reports

......

Z
Zoltan Palffy 👤 Member for 16 years 10 months

#7 can be via a histogram if you set your max limit

the other way to do it is to export the histogram or the curve to excel and add the current available manpower that you currently have availabe into the excel graph.

D
Dennis Hanks 👤 Member for 19 years 1 month

Zoltan: Nice list. How is #7 developed? I assume it is more than just the resource spreadsheet. Thanks.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

You need to tailor your reports to your audience.

1. Since this is management then an overall summary schedule would be beneficial.

2. A critical path schedule (only showing critical activites) would be beneficial.

3. A near term critical path schedule (only showing critical activites and NEAR criitcal) would be beneficial to be used to plan against.

4. An schedule exception report only items behind schedule.

5. A cost exception report only items over budget.

6. A cash flow curve

7. Current available vs current anticipated manpower histogram

8. Overall schedule that compaires baseline vs current schedule

9. Schedule that is filtered for additional work only.

10. A Monthly schedule narrative 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts