Hi members,
Can you please mail me a programme which is cost loaded in P6.
I am monitoring progress based on labour units as the project am working on with doesnt have a finalised BOQ.
I want to know how monitoring can be effectively done with cost loaded programme.
Please mail to [email protected]. Thanks in advance.
Adding, which is the best way to monitor progress either with cost or labour units?? and why?
Regards,
Tasha
Hi Tasha,
If your activity is 100% complete then EV will be equal to actual cost of that of that that particular activity.
Regards,
Sunil.
Dear All,
Can you please mail me a programme which is cost loaded in P6.
To monitor effectively with cost loaded programme.
Please mail to [email protected]
Regards,
Anish
Hi All,
Can you also havea XER file of the cost loaded file? [email protected]
Endralie Halog
Dear Memebers,
Can you please mail me a Sample programme P6.
I want to know about Safron Project 5.
Please mail to [email protected]
Thanks and Regards,
Teja
Yes if Auto Compute Actuals is enabled and Activity % Complete based on Activity Steps is disabled.
Thank You very much Mr Raymund.
When I update the Activity % complete, does EV becomes equal to Actual Cost of the particular activity?
Tasha,
Assign a Resource with a Dollar U/P and 1 Budgeted Unit in every Resource while waiting for the BOQ.
Monitor the Progress base on Physical Accomplishment.
Regards,