Sample P6 Programme with cost Loading

Hi members,

Can you please mail me a programme which is cost loaded in P6.

I am monitoring progress based on labour units as the project am working on with doesnt have a finalised BOQ.

I want to know how monitoring can be effectively done with cost loaded programme.

Please mail to [email protected]. Thanks in advance.

Adding, which is the best way to monitor progress either with cost or labour units?? and why?

Regards,

Tasha

S
Sunil Babu 👤 Member for 15 years 6 months

Hi Tasha,

If your activity is 100% complete then EV will be equal to actual cost of that of that that particular activity.

Regards,

Sunil.

R
Raymund de Laza 👤 Member for 16 years 6 months

Yes if Auto Compute Actuals is enabled and Activity % Complete based on Activity Steps is disabled.

T
Tasha Harrison 👤 Member for 12 years

Thank You very much Mr Raymund.

When I update the Activity % complete, does EV becomes equal to Actual Cost of the particular activity?

R
Raymund de Laza 👤 Member for 16 years 6 months

Tasha,

Assign a Resource with a Dollar U/P and 1 Budgeted Unit in every Resource while waiting for the BOQ.

Monitor the Progress base on Physical Accomplishment.

 

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts