Activity Relationships

R
Richard Day 👤 Member for 17 years 11 months

The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13   Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?

M
Mike Testro 👤 Member for 20 years 6 months

Hi Richard

What you have is a ladder effect which is common in manufacturing but has no real place in construction.

It should make no difference to the operation of the logic and it could be beneficial when a progress up date goes beyond the SS link.

Best regards

Mike T.

Forum Sponsor

Top Posters

Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts