is the phrase" Scehdule dose not supporting Claims' is a right statement or not?
Cliams
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Muhhammad.
Having been involved in delay analysis for the last 18 years I have only seen two baseline programmes that were fit for delay analysis without any form of adjustments - and they were both tender programmes that I prepared for the contractor.
So the answer to your question is YES - every contrator's baseline programme does not support claims.
Best regards
Mike Testro