Cliams

is the phrase" Scehdule dose not supporting Claims' is a right statement or not?

M
Mike Testro 👤 Member for 20 years 6 months

Hi Muhhammad.

Having been involved in delay analysis for the last 18 years I have only seen two baseline programmes that were fit for delay analysis without any form of adjustments - and they were both tender programmes that I prepared for the contractor.

So the answer to your question is YES - every contrator's baseline programme does not support claims.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts