Cliams

is the phrase" Scehdule dose not supporting Claims' is a right statement or not?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Muhhammad.

Having been involved in delay analysis for the last 18 years I have only seen two baseline programmes that were fit for delay analysis without any form of adjustments - and they were both tender programmes that I prepared for the contractor.

So the answer to your question is YES - every contrator's baseline programme does not support claims.

Best regards

Mike Testro