Dear all,
When can I start Staircase work
1.Ground floor slab
2 .Columns
3 .beams
4. RCC walls
5. First Floor Slab
------------------------------
6 .Columns
7.Beams
8. RCC walls
9.Roof Slab
From where i can start RCC staircase construction
Thanks
Dear all,
When can I start Staircase work
1.Ground floor slab
2 .Columns
3 .beams
4. RCC walls
5. First Floor Slab
------------------------------
6 .Columns
7.Beams
8. RCC walls
9.Roof Slab
From where i can start RCC staircase construction
Thanks
Hi Saju
You have to have at least two slabs to support the staircase and it can follow the structure upwards.
It depends on the construction method statement because the stairwell may be used for vertical access and hoists.
I would also consider a precast option which can be dropped into place in one day.
Best regards
Mike Testro