I understand that upon approval of baseline, it seves as a contractual document.
How about S curve and Manpower histogram ? Does it constitute of a committment to comply with the manpower, equipment and performance aspect?
Does it work against us if the actual deviate too much from the planned ?
And does it relate to acceleration cost calculation etc?
Dear
There are two types of progress measurement a) Based on man days b) Based on cost
S curve is basically progress measurement , for that you have to load man days or cost in order to generate S curve
Base line is a program plan that include man pwer plan, machine plan, and cost plan, it is basically for measuring deviation from actuals.
If there is deviation, next program is a recovery program with more productivity ( more resource and less time).
How ever the loading is purely depeds on the client consultant, or internal reporting need