Programme, S curve Manpower Histogram

T
TII WS 👤 Member for 16 years 4 months

I understand that upon approval of baseline, it seves as a contractual document.

How about S curve and Manpower histogram ? Does it constitute of a committment to comply with the manpower, equipment and performance aspect?

Does it work against us if the actual deviate too much from the planned ?

And does it relate to acceleration cost calculation etc?

S
Saju TS 👤 Member for 16 years 11 months

Dear

There are two types of progress measurement a) Based on man days  b) Based on cost

 S curve is basically progress measurement , for that you have to load man days or cost in order to generate  S curve

Base line is a program plan that include man pwer plan, machine plan, and cost plan, it is basically for measuring deviation from actuals.

If there is deviation, next program is a recovery program with more productivity ( more resource and less time).

How ever the loading is purely depeds on the client consultant, or internal reporting need

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts