Hi, everyone. What duration type you will choose? then what percentage type you will use to engage your duration type. Or it is

L
louis hung 👤 Member for 18 years 1 month

 

Regarding you had completed resource loading and been authorized of your baseline.1.Fix Duration &Units2.Fix Duration &Units/time3.Fix units4.Fix Units/timeThen what percentage type you usually adopt.1.Duration2.Physical 3.Unit.Actually, I am not very sure how it engage this two elements to make it work well.Maybe you guy can provide your well experience here.Thanks!

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Louis

If your schedule if resource loaded i suggest that you use Physical percentage type. The advantage is that you can spit the remaining duration and the % completion. This is particularly useful when you apply Earned Value Techniques. The disadvantage is that you have to update every single activity and apply remaining duration and % complete.  

Johannes

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts