Hey,
Anyone could help me how to incorporate the milestone or activity repeating only for 4 hours in a week on the same time and on the same day.?
Lets suppose if the project is of 10 weeks, and i have a project meeting of 2 hours on each monday, then how to incorporate it into the program under a single WBS?... shall i have to write meetins activity 10 times or there is any other solution?.
Pleas ehelp,
regards, KK
thanx Daniel, thats a useful tip though.
Hi Kashif,
If working unit in P6 is on an hourly basis then you can incorporate it as an activity. If minimum is a day, then you can use your calendar and block those hours, go to calendars and click detailed working hours, the problem though it will no show in your programme.
Regards,
Daniel