Repeated milestone/ activity

K
Kashif Khan 👤 Member for 14 years 7 months

Hey,

 

Anyone could help me how to incorporate the milestone or activity repeating only for 4 hours in a week on the same time and on the same day.?

Lets suppose if the project is of 10 weeks, and i have a project meeting of 2 hours on each monday, then how to incorporate it into the program under a single WBS?... shall i have to write meetins activity 10 times or there is any other solution?.

Pleas ehelp,

regards, KK

D
Daniel Limson 👤 Member for 24 years 8 months

Hi Kashif,

If working unit in P6 is on an hourly basis then you can incorporate it as an activity. If minimum is a day, then you can use your calendar and block those hours, go to calendars and click detailed working hours, the problem though it will no show in your programme.

Regards,

Daniel

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts