What is the right predecessor for these activities?

My predecessor for the activity "Prepare RFQ (Request for Quotation) of Equipment xxx" in mechanical engineering is the activity "Prepare Data Sheet of Equipment xxx" in process engineering. Basically all my RFQ preparation activities for mechanical equipments have the same type of predecessor (linked to the corresponding Data Sheet in process).

I'd like to know the same for the electrical equipment. Which would be the best predecessor for the activity in which the electrical engineers start preparing the information to go for RFQ of those equipments? Preliminary Electrical Equipment List? Preliminary Electrical Line List?

Also, what would be the best predecessor for materials in this case? (cables, cable trays, etc.) The MTO (Materials Take-Off) deliverable?

J
Jose Frade 👤 Member for 21 years

Hi John

It depends on the equipment / activity it self, Ex:

 

Piping: Need pipe take of lists

Cables - Need cable spec + Cable list + (which require consumer list on its turn).

Cable trays - Need cable tray spec + cable tray Qtys (which need cable tray layout drg on its turn)

Transformer - Need Data sheet (Which need consumer list, etc)

 

In general for electrical the preliminary equipment list is a good start to define what is required for each type of equipment.

 

In all of the above (as well as for mechanical) the Comercial guys also need to prepare the comercial attachements - which go along with the enquire. Also remember to include with the datasheets the relevant technical engineering information concerning interface point definition - otherwise you might end-up having a square duct to connect with a round blower outlet.

 

BR

 

JMFrade

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts