Changing the Data Date and its Impression on Project Milestones

E
Ed Afkham 👤 Member for 14 years 9 months

 

Changing the data date shouldn’t practically push back project milestones.

How do you justify that considering the fact that it pushes back not started activities the same period of data date? 

F
Forrest Chen 👤 Member for 14 years 5 months

Hi,

If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';

as for other activities, you can either constrain them (not recommended) or logically link them together.

Hope the above helps with you question.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts