Changing the data date shouldn’t practically push back project milestones.
How do you justify that considering the fact that it pushes back not started activities the same period of data date?
Changing the data date shouldn’t practically push back project milestones.
How do you justify that considering the fact that it pushes back not started activities the same period of data date?
Hi,
If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';
as for other activities, you can either constrain them (not recommended) or logically link them together.
Hope the above helps with you question.