Change must end by date

D
Dave Scott 👤 Member for 14 years 6 months

I recently built a schedule in P6 that had an must end by date of July 23, 2012.

Shortly there after, additional work and time was added to the project.

How can I add the 6 extra weeks to my schedule?  I need to move the must end by date out by an additional 6 weeks.

Thanks,

Dave

G
Gary Whitehead 👤 Member for 17 years 3 months

Dave,

 

From Enterprise > Projects, highlight the relevant project.

Then go to View > Show on Bottom > Project Details

Go to the "Dates" tab of the Project Details, and you can ammend your Must Finish By date here.

 

Cheers,

 

G

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts