I recently built a schedule in P6 that had an must end by date of July 23, 2012.
Shortly there after, additional work and time was added to the project.
How can I add the 6 extra weeks to my schedule? I need to move the must end by date out by an additional 6 weeks.
Thanks,
Dave
Dave,
From Enterprise > Projects, highlight the relevant project.
Then go to View > Show on Bottom > Project Details
Go to the "Dates" tab of the Project Details, and you can ammend your Must Finish By date here.
Cheers,
G