Maintaining baselines

R
Rhys Parry 👤 Member for 14 years 8 months

Hello

Just a quick Question regarding baselining my project.

When I schedule my project and then I baseline it with that data date.

If I then update the project plan and schedule it with a new data date and baseline it again is it possible to go back to the previous baseline to see the original plan instead of clicking on Undo if things don't go correct  after I schedule & resource level.

Thanks

 

Rhys

S
Simon Willson 👤 Member for 19 years 6 months

Hi Rhys,

If you are wanting to keep an archive of baselines, I would take the following action.

  1. Base line your schedule.
  2. Perform your updates as required.
  3. At the time you need to update your baseline (i.e. as a result of approved change control or directed by senior stakeholders), remove the baseline from the current schedule.
  4. Make a copy of the baseline and call it something like Baseline 1 (or what ever serial is appropriate).  Up rev / issue the copy and call it Baseline 2. 
  5. Update baseline 2 to reflect the required change.
  6. Schedule baseline 2 with the appropriate datadate.  Remember, if you are going to progress the data date and activities have started, you will have to update progress in the baseline copy accordingly.
  7. Reattach both baselines to the master schedule, baseline 2 will be the project baseline, baseline 1 as a user baseline.

You can now compare one against the other.  If the changes are appropriate you can keep baseline 2 but if things aren't right, you still have the option of going back to the original baseline.

Hope this helps.

 

Simon

R
Rhys Parry 👤 Member for 14 years 8 months

Just within Primavera 6 Version 2

Sorry forgot to mention that

Rhys

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts