Hello
Just a quick Question regarding baselining my project.
When I schedule my project and then I baseline it with that data date.
If I then update the project plan and schedule it with a new data date and baseline it again is it possible to go back to the previous baseline to see the original plan instead of clicking on Undo if things don't go correct after I schedule & resource level.
Thanks
Rhys
Right Ok
Thanks for your help Simon
Rhys
Hi Rhys,
If you are wanting to keep an archive of baselines, I would take the following action.
You can now compare one against the other. If the changes are appropriate you can keep baseline 2 but if things aren't right, you still have the option of going back to the original baseline.
Hope this helps.
Simon
Just within Primavera 6 Version 2
Sorry forgot to mention that
Rhys
Hi Rhys
What software?
Best regards
Mike Testro